Construction progress on the IPF/Bubble
None

I cycled through campus today and went to look at the new facility. There is no sign of anything. No flags, no stakes, no markings I could see. I thought they were trying to get it finished in August. I cannot see how that happens now.
07-21-2019 11:45 AM
Find all posts by this user Quote this message in a reply
Advertisement


Ourland Offline
Heisman
*

Posts: 6,604
Joined: Apr 2017
Reputation: 307
I Root For: The Rice Owls
Location: Galveston
Post: #2
RE: Construction progress on the IPF/Bubble
Disappointing to hear
07-22-2019 12:14 AM
Find all posts by this user Quote this message in a reply
gsloth Offline
perpetually tired
*

Posts: 6,654
Joined: Aug 2007
Reputation: 54
I Root For: Rice&underdogs
Location: Central VA

Donators
Post: #3
RE: Construction progress on the IPF/Bubble
Maybe they're testing the quick-up nature of the bubble? Going to put it up just-in-time for football practices in August? And when does women's soccer practice start? They may need it, too.

*scratching his head for any other possible positive spins on it*
07-22-2019 08:20 AM
Find all posts by this user Quote this message in a reply
Owl 69/70/75 Offline
Just an old rugby coach
*

Posts: 80,797
Joined: Sep 2005
Reputation: 3211
I Root For: RiceBathChelsea
Location: Montgomery, TX

DonatorsNew Orleans Bowl
Post: #4
RE: Construction progress on the IPF/Bubble
Rice has never done facilities well or right, at least not since I first got to the university. You'd expect that to change now?
07-22-2019 08:35 AM
Find all posts by this user Quote this message in a reply
Frizzy Owl Online
Heisman
*

Posts: 9,341
Joined: Nov 2012
Reputation: 54
I Root For: Rice
Location:
Post: #5
RE: Construction progress on the IPF/Bubble
In the February Thresher article, Mello was noncommittal on the completion date. He said it could be as early as August if the $3 million in donations was received in time.
07-22-2019 08:37 AM
Find all posts by this user Quote this message in a reply
TFW Offline
All American
*

Posts: 3,235
Joined: Jun 2005
Reputation: 29
I Root For: Owls in Omaha
Location: 2nd Base

New Orleans BowlDonators
Post: #6
RE: Construction progress on the IPF/Bubble
(07-22-2019 08:37 AM)Frizzy Owl Wrote:  In the February Thresher article, Mello was noncommittal on the completion date. He said it could be as early as August if the $3 million in donations was received in time.

So it's sort of like building a highway... they will start as soon as the money is available.
07-22-2019 11:48 AM
Find all posts by this user Quote this message in a reply
Advertisement


Frizzy Owl Online
Heisman
*

Posts: 9,341
Joined: Nov 2012
Reputation: 54
I Root For: Rice
Location:
Post: #7
RE: Construction progress on the IPF/Bubble
(07-22-2019 11:48 AM)TFW Wrote:  
(07-22-2019 08:37 AM)Frizzy Owl Wrote:  In the February Thresher article, Mello was noncommittal on the completion date. He said it could be as early as August if the $3 million in donations was received in time.

So it's sort of like building a highway... they will start as soon as the money is available.

Well, yes, of course.
07-22-2019 12:30 PM
Find all posts by this user Quote this message in a reply
texowl2 Offline
All American
*

Posts: 3,077
Joined: Jun 2005
Reputation: 33
I Root For:
Location:

New Orleans Bowl
Post: #8
RE: Construction progress on the IPF/Bubble
Nothing like announcing total victory before being engaged or even knowing what you are involved in. Such is the not for profit world of irreality, total fantasy and OPM. I'm announcing that I will be donating 10% of my lottery winnings. Would that be helpful?

OPM stands for other people's money.
07-22-2019 01:30 PM
Find all posts by this user Quote this message in a reply
Frizzy Owl Online
Heisman
*

Posts: 9,341
Joined: Nov 2012
Reputation: 54
I Root For: Rice
Location:
Post: #9
RE: Construction progress on the IPF/Bubble
(07-22-2019 01:30 PM)texowl2 Wrote:  Nothing like announcing total victory before being engaged or even knowing what you are involved in. Such is the not for profit world of irreality, total fantasy and OPM. I'm announcing that I will be donating 10% of my lottery winnings. Would that be helpful?

OPM stands for other people's money.

Who announced total victory?

Of course it's other people's money. No money trees on campus.
07-22-2019 01:37 PM
Find all posts by this user Quote this message in a reply
mebehutchi Offline
Special Teams
*

Posts: 548
Joined: Dec 2005
Reputation: 14
I Root For:
Location:
Post: #10
RE: Construction progress on the IPF/Bubble
I think the money is there unless something has changed recently. They may have been a bit naive with the permitting.
07-22-2019 02:33 PM
Find all posts by this user Quote this message in a reply
waltgreenberg Online
Legend
*

Posts: 33,265
Joined: Feb 2006
Reputation: 141
I Root For: Rice Owls
Location: Chicago

The Parliament Awards
Post: #11
RE: Construction progress on the IPF/Bubble
(07-22-2019 02:33 PM)mebehutchi Wrote:  I think the money is there unless something has changed recently. They may have been a bit naive with the permitting.

Yes, the money has been secured.
07-22-2019 03:21 PM
Find all posts by this user Quote this message in a reply
Advertisement


OldOwl Offline
1st String
*

Posts: 2,315
Joined: Oct 2011
Reputation: -12
I Root For: Rice Owls
Location:
Post: #12
RE: Construction progress on the IPF/Bubble
Whats going on with the bubble? When will construction start?
08-03-2019 05:41 PM
Find all posts by this user Quote this message in a reply
westsidewolf1989 Offline
Heisman
*

Posts: 6,230
Joined: Dec 2008
Reputation: 74
I Root For: Rice
Location:
Post: #13
RE: Construction progress on the IPF/Bubble
(08-03-2019 05:41 PM)OldOwl Wrote:  Whats going on with the bubble? When will construction start?

Heard the check to buy the air pump from Academy is in the mail.
08-03-2019 10:34 PM
Find all posts by this user Quote this message in a reply
wiessguy Offline
1st String
*

Posts: 1,223
Joined: Aug 2007
Reputation: 9
I Root For: Da Owls
Location: Houston, TX
Post: #14
RE: Construction progress on the IPF/Bubble
We don’t need the bubble til recruiting season anyway...
08-03-2019 10:36 PM
Find all posts by this user Quote this message in a reply
texowl2 Offline
All American
*

Posts: 3,077
Joined: Jun 2005
Reputation: 33
I Root For:
Location:

New Orleans Bowl
Post: #15
RE: Construction progress on the IPF/Bubble
well at least the greenbriar construction seems to be in the final legs with the section between Rice and University closest to the stadium now open. Guess the deadline to finish the whole section from University to Holcombe must be close. After months of nothing, they seemed to have woken up. Horrible written contract to allow them so much time. The Empire State Building was built in less time than Greenbriar
08-04-2019 06:46 AM
Find all posts by this user Quote this message in a reply
TexasTerror Offline
1st String
*

Posts: 2,486
Joined: Jun 2010
Reputation: 91
I Root For: SHSU
Location:
Post: #16
RE: Construction progress on the IPF/Bubble
(08-04-2019 06:46 AM)texowl2 Wrote:  well at least the greenbriar construction seems to be in the final legs with the section between Rice and University closest to the stadium now open. Guess the deadline to finish the whole section from University to Holcombe must be close. After months of nothing, they seemed to have woken up. Horrible written contract to allow them so much time. The Empire State Building was built in less time than Greenbriar

If you traverse the whole length, there’s still 2 or 3 sections left to do including one side of the street between Rice and University. The project is scheduled to be concluded by December. The parts south of Roberts Elementary were done beautifully. Will be a great day once the whole darn thing is complete. It’s led more folks to drive through Rice’a campus, complete mess between Christ the King and Island Grill and don’t get me started on some of Morningside issues by Holcombe
08-06-2019 07:51 AM
Find all posts by this user Quote this message in a reply
Advertisement


Ourland Offline
Heisman
*

Posts: 6,604
Joined: Apr 2017
Reputation: 307
I Root For: The Rice Owls
Location: Galveston
Post: #17
RE: Construction progress on the IPF/Bubble
Any activity yet?
08-20-2019 05:59 PM
Find all posts by this user Quote this message in a reply
dragon2owl Online
Heisman
*

Posts: 8,164
Joined: Jan 2009
Reputation: 37
I Root For: RICE
Location: Houston
Post: #18
RE: Construction progress on the IPF/Bubble
Quote:The construction of Rice Athletics’ indoor practice facility has been delayed and is not expected to be completed until after Beer Bike, according to Deputy Athletic Director Rick Mello. Mello said the primary reason for the delay has been difficulty with establishing electronic circuitry to the facility, and a misunderstanding between Rice and its electrical contractor.

https://www.ricethresher.org/article/201...MbdxhAenbI
10-04-2019 10:35 AM
Find all posts by this user Quote this message in a reply
OptimisticOwl Offline
Legend
*

Posts: 58,658
Joined: Apr 2005
Reputation: 857
I Root For: Rice
Location: DFW Metroplex

The Parliament AwardsNew Orleans BowlFootball GeniusCrappiesDonatorsDonators
Post: #19
RE: Construction progress on the IPF/Bubble
(10-04-2019 10:35 AM)dragon2owl Wrote:  
Quote:The construction of Rice Athletics’ indoor practice facility has been delayed and is not expected to be completed until after Beer Bike, according to Deputy Athletic Director Rick Mello. Mello said the primary reason for the delay has been difficulty with establishing electronic circuitry to the facility, and a misunderstanding between Rice and its electrical contractor.

https://www.ricethresher.org/article/201...MbdxhAenbI

Let's get our friends in the IBEW in on this.
10-04-2019 10:43 AM
Find all posts by this user Quote this message in a reply
Pan95 Offline
All American
*

Posts: 2,688
Joined: Jan 2009
Reputation: 56
I Root For: Rice/WY
Location:
Post: #20
RE: Construction progress on the IPF/Bubble
(10-04-2019 10:43 AM)OptimisticOwl Wrote:  
(10-04-2019 10:35 AM)dragon2owl Wrote:  
Quote:The construction of Rice Athletics’ indoor practice facility has been delayed and is not expected to be completed until after Beer Bike, according to Deputy Athletic Director Rick Mello. Mello said the primary reason for the delay has been difficulty with establishing electronic circuitry to the facility, and a misunderstanding between Rice and its electrical contractor.

https://www.ricethresher.org/article/201...MbdxhAenbI

Let's get our friends in the IBEW in on this.

Even more of a reason to build a permanent facility.
10-04-2019 01:13 PM
Find all posts by this user Quote this message in a reply
Post Reply 




User(s) browsing this thread: 1 Guest(s)


Copyright © 2002-2024 Collegiate Sports Nation Bulletin Board System (CSNbbs), All Rights Reserved.
CSNbbs is an independent fan site and is in no way affiliated to the NCAA or any of the schools and conferences it represents.
This site monetizes links. FTC Disclosure.
We allow third-party companies to serve ads and/or collect certain anonymous information when you visit our web site. These companies may use non-personally identifiable information (e.g., click stream information, browser type, time and date, subject of advertisements clicked or scrolled over) during your visits to this and other Web sites in order to provide advertisements about goods and services likely to be of greater interest to you. These companies typically use a cookie or third party web beacon to collect this information. To learn more about this behavioral advertising practice or to opt-out of this type of advertising, you can visit http://www.networkadvertising.org.
Powered By MyBB, © 2002-2024 MyBB Group.