Blue Oval news: Ford delays new EV plant - Claw - 08-21-2024 01:21 PM

There's a bump in the road for Blue Oval development.

Ford delays new EV plant, cancels electric three-row SUV as it shifts strategy

Quote:KEY POINTS
Vehicle production at the new plant in Tennessee was initially expected to begin next year.
The company said it still expects to begin battery cell production at the site in 2025.
Ford CFO John Lawler said the shifts are meant to better deliver a capital-efficient, profitable electric vehicle business.

Quote:DETROIT – Ford Motor
is delaying production of a next-generation all-electric pickup truck at a new plant in Tennessee and canceling plans for a three-row electric SUV, the company said Wednesday.

Instead, Ford said it will prioritize the development of hybrid models, as well as electric commercial vehicles such as a new electric commercial van in 2026, followed by two EV pickup trucks in 2027.

The pickups are expected to be a full-size truck, which will be produced in 2027 at the Tennessee plant that’s currently under construction, and a new midsize truck being developed by a specialized “skunkworks” team in California.



RE: Blue Oval news: Ford delays new EV plant - MemTigers1998 - 08-21-2024 01:24 PM

I’ll be shocked if any vehicles are ever made there. Give it 5-10 years and that site will be an overgrown vacant place that the locals will have bonfires on the weekends.


RE: Blue Oval news: Ford delays new EV plant - tigerlands - 08-21-2024 02:21 PM

Yeah, it's kind of a "uh-oh" moment. But I don't see a company like Ford not finding a way to make it work. Maybe just not on the scale that was first announced.


RE: Blue Oval news: Ford delays new EV plant - BERT56 - 08-21-2024 02:24 PM

(08-21-2024 02:21 PM)tigerlands Wrote:  Yeah, it's kind of a "uh-oh" moment. But I don't see a company like Ford not finding a way to make it work. Maybe just not on the scale that was first announced.

Do they not know about our airport?!?!?!


RE: Blue Oval news: Ford delays new EV plant - Lord2FLI - 08-21-2024 02:53 PM

Ford is going to get burned going all in on trucks and SUVs (both gas and EV), should have kept stuff like the Fusion and Fiesta around for EV


RE: Blue Oval news: Ford delays new EV plant - ncrdbl1 - 08-21-2024 02:57 PM

(08-21-2024 01:21 PM)Claw Wrote:  There's a bump in the road for Blue Oval development.

Ford delays new EV plant, cancels electric three-row SUV as it shifts strategy

Quote:KEY POINTS
Vehicle production at the new plant in Tennessee was initially expected to begin next year.
The company said it still expects to begin battery cell production at the site in 2025.
Ford CFO John Lawler said the shifts are meant to better deliver a capital-efficient, profitable electric vehicle business.

Quote:DETROIT – Ford Motor
is delaying production of a next-generation all-electric pickup truck at a new plant in Tennessee and canceling plans for a three-row electric SUV, the company said Wednesday.

Instead, Ford said it will prioritize the development of hybrid models,
as well as electric commercial vehicles such as a new electric commercial van in 2026, followed by two EV pickup trucks in 2027.

The pickups are expected to be a full-size truck, which will be produced in 2027 at the Tennessee plant that’s currently under construction, and a new midsize truck being developed by a specialized “skunkworks” team in California.

Something that anyone with any commonsense would have done.

EV will never be more than a gimmick as long as they rely on stored energy.

EV must be able to produce their own energy on demand before they will truly be practical.

Electrical components show no signs of wear and tear as ICE components do.

You can test drive an ICE vehicle, take it to your mechanic and more or less know the condition of the vehicle.

Not so with EV.

Internationally more and more manufacturers are investing in hydrogen fuel cell technology.


RE: Blue Oval news: Ford delays new EV plant - Lord2FLI - 08-21-2024 02:59 PM

(08-21-2024 02:57 PM)ncrdbl1 Wrote:  
(08-21-2024 01:21 PM)Claw Wrote:  There's a bump in the road for Blue Oval development.

Ford delays new EV plant, cancels electric three-row SUV as it shifts strategy

Quote:KEY POINTS
Vehicle production at the new plant in Tennessee was initially expected to begin next year.
The company said it still expects to begin battery cell production at the site in 2025.
Ford CFO John Lawler said the shifts are meant to better deliver a capital-efficient, profitable electric vehicle business.

Quote:DETROIT – Ford Motor
is delaying production of a next-generation all-electric pickup truck at a new plant in Tennessee and canceling plans for a three-row electric SUV, the company said Wednesday.

Instead, Ford said it will prioritize the development of hybrid models,
as well as electric commercial vehicles such as a new electric commercial van in 2026, followed by two EV pickup trucks in 2027.

The pickups are expected to be a full-size truck, which will be produced in 2027 at the Tennessee plant that’s currently under construction, and a new midsize truck being developed by a specialized “skunkworks” team in California.

Something that anyone with any commonsense would have done.

EV will never be more than a gimmick as long as they rely on stored energy.

EV must be able to produce their own energy on demand before they will truly be practical.

Electrical components show no signs of wear and tear as ICE components do.

You can test drive an ICE vehicle, take it to your mechanic and more or less know the condition of the vehicle.

Not so with EV.

Internationally more and more manufacturers are investing in hydrogen fuel cell technology.

I love my hybrid, best of both worlds, I get 45/mpg (well more like 42 because I brake fast) and don't have to plug it in anywhere.


RE: Blue Oval news: Ford delays new EV plant - ncrdbl1 - 08-21-2024 03:07 PM

(08-21-2024 02:59 PM)Lord2FLI Wrote:  
(08-21-2024 02:57 PM)ncrdbl1 Wrote:  
(08-21-2024 01:21 PM)Claw Wrote:  There's a bump in the road for Blue Oval development.

Ford delays new EV plant, cancels electric three-row SUV as it shifts strategy

Quote:KEY POINTS
Vehicle production at the new plant in Tennessee was initially expected to begin next year.
The company said it still expects to begin battery cell production at the site in 2025.
Ford CFO John Lawler said the shifts are meant to better deliver a capital-efficient, profitable electric vehicle business.

Quote:DETROIT – Ford Motor
is delaying production of a next-generation all-electric pickup truck at a new plant in Tennessee and canceling plans for a three-row electric SUV, the company said Wednesday.

Instead, Ford said it will prioritize the development of hybrid models,
as well as electric commercial vehicles such as a new electric commercial van in 2026, followed by two EV pickup trucks in 2027.

The pickups are expected to be a full-size truck, which will be produced in 2027 at the Tennessee plant that’s currently under construction, and a new midsize truck being developed by a specialized “skunkworks” team in California.

Something that anyone with any commonsense would have done.

EV will never be more than a gimmick as long as they rely on stored energy.

EV must be able to produce their own energy on demand before they will truly be practical.

Electrical components show no signs of wear and tear as ICE components do.

You can test drive an ICE vehicle, take it to your mechanic and more or less know the condition of the vehicle.

Not so with EV.

Internationally more and more manufacturers are investing in hydrogen fuel cell technology.

I love my hybrid, best of both worlds, I get 45/mpg (well more like 42 because I brake fast) and don't have to plug it in anywhere.

And the basic technology has been around for over 100 years.

Our sub fleets before they went nuclear worked on hybrid systems.


RE: Blue Oval news: Ford delays new EV plant - Unionman76 - 08-21-2024 03:16 PM

there is another blue oval being built in glendale, ky (i-65 south of Elizabethtown )

https://www.google.com/maps/@37.5849812,-85.8702916,3502m/data=!3m1!1e3?entry=ttu


RE: Blue Oval news: Ford delays new EV plant - umbluegray - 08-21-2024 03:19 PM

(08-21-2024 03:16 PM)Unionman76 Wrote:  there is another blue oval being built in glendale, ky (i-65 south of Elizabethtown )

https://www.google.com/maps/@37.5849812,-85.8702916,3502m/data=!3m1!1e3?entry=ttu

That was just the battery plant. They paused that a year ago or so. We're lucky to have gotten the car and battery plants here.


They're waiting to see the election outcome. One administration is going to force EVs, the other will say EVs, Hybrids, gas... whatever.

Once we make our decision in November, Ford will make their decision.


RE: Blue Oval news: Ford delays new EV plant - CKMcDan - 08-21-2024 03:31 PM

Ford halting production on an electric 3-row SUV makes perfect sense. Why anyone thought an electric "people-hauler" makes sense is beyond me.

The two main drawbacks of an EV are range and charge time. Families buy these 3-row SUV's and minivans to haul kids around town, and to pack up the fam for a long trip. Yes, I spend more in gas driving my family to Destin, but at least I get there in 8-9 hrs, vs. the added time stopping to charge (and hoping you can find a charger) would add to that long haul.

I can certainly see the advantage of having an EV to drive locally, and to work. But, for long trips, I want an ICE, or at least a hybrid.


RE: Blue Oval news: Ford delays new EV plant - mapdude - 08-23-2024 08:39 AM

In the long run, Ford will build something at that plant, either EV or ICE.

And parts do wear out on EV. They have brakes, belts, compressors, etc.


RE: Blue Oval news: Ford delays new EV plant - Cletus - 08-23-2024 11:33 AM

.
This guy shoots from the hip & is mostly always correct.
He used to drive me crazy but he's grown on me. lol
Lives part of the year in Rhode Island & the other above Nashville in Clarksville.






RE: Blue Oval news: Ford delays new EV plant - Unionman76 - 08-23-2024 12:42 PM

All those unsold fords are parked at Kentucky speedway


RE: Blue Oval news: Ford delays new EV plant - TigerBlue4Ever - 09-14-2024 06:55 AM

(08-21-2024 01:24 PM)MemTigers1998 Wrote:  I’ll be shocked if any vehicles are ever made there. Give it 5-10 years and that site will be an overgrown vacant place that the locals will have bonfires on the weekends.

That's my thought as well.


RE: Blue Oval news: Ford delays new EV plant - Claw - 12-12-2025 09:51 AM

More news. The big dream for West Tennessee is faltering, but not dead yet.

South Korean battery giant ends partnership with Ford’s Blue Oval City


Quote:MEMPHIS, Tenn. — South Korean battery giant SK On is ending its partnership with the Ford Motor Company and will take over BlueOval City, Reuters is reporting.

SK On said on Thursday that the companies would split three massive battery factories, with SK On taking the one in Stanton, Tennessee.

Ford will take ownership of two battery plants in Kentucky.
.
.
.

Ford is set to produce its new electric pickup trucks at the Stanton Plant, but the start of mass production has been pushed back to 2028.



RE: Blue Oval news: Ford delays new EV plant - yakko - 12-12-2025 01:35 PM

Might actually be a benefit, being able to make batteries for more than just Ford would open up options.